Job consists
of three locations: NW Complex, I-35 Complex and the
College Complex. NW Complex - Build new 125 dia. Ground
storage tank and piping with a drain box. Around 2000 LF of
RJ and MJ yard piping (24" & 36"). Build new pump station
structure with 4-300 hp split-case pumps and piping. New
sodium hypochlorite tank and structure. New chemical feed
vault and 2 meter vaults. New transformer and generator.
I-35 Complex - Add on to existing pump station. Add 2-400
hp vertical turbine pumps and piping. Demo existing meter
vault and construct 2 new vaults and one sleeve valve
vault. Lay new pipe from pump station to under existing
ground storage tank. Lay approx. 270 LF of 24" yard
piping. New transformer. College Complex - New sodium
hypochlorite tank and structure. New meter vault. Lay
small chemical feed yard piping. Drain, clean, and
disinfect existing ground storage tank.
Furnish and
install approx. 8500 lf of 30" DIP waterline and
appurtenances. Furnish and install approx. 170 lf of 48"
Bored Crossing. Furnish and install approx. 370 lf of 48"
steel cased creek crossings. Miscelleanous tie-ins and
pavement replacement.
Furnish &
install approx. 16,000 lf of 30" DIP, 5 poured in place BFU
Vaults, 2 each Air Release Vaults, 5 each Blow-off
connections. Remove and replace approx. 1550 SY of
pavement. Install 48" Bore.
|