OAKLEY
AVENUE WATERLINE
City of Topeka, Kansas
Bartlett & West Engineers
Currently
Under Construction
$4,898,000
Construction
of water main extension consisting of approximately 11,200'
of 42" dia. DIP and 1306' DIP water main, valves, fittings,
fire hydrant setting, 235' of 51" dia. Road Bore, 16,600 SY
of pavement replacement, system Interconnections, and
appurtenances. Several large areas of street, sidewalk,
curb & gutter replacement were included. This project lays
in the street, and is located in a business and residential
area. Town meetings were conducted to keep the public
informed and public relations was a significant component of
the project.
|