WWTP
TONGANOXIE, KANSAS
City
of Tonganoxie, Kansas
BG
Consultants, Manhattan, Kansas
Completed
2005
$2,777,530
This project
included
site
grading, access roads, construction of influent pump
station, headworks building with washer/compactor and
automated bar screen, vortex grit chamber with grit
classifier, North and South splitter boxes, aeration basin,
clarifiers, UV disinfection and building, non-potable water
pump station, cascade, RAS/WAS pump station and building,
scum pump station, process building with laboratory, MCC
room, office, break room, maintenance, etc., piping, valves,
and all associated appurtenances.
While the project was first let in March
2003, the day that the United States declared war with Iraq,
all bids were rejected due to economic uncertainty. With a
limited amount of funding for this project, and the fact of
war now driving prices skyward, the City of Tonganoxie was
interested in finding innovative means and methods of
maximizing their use of available funds. BG was able to
assist the City in purchasing almost $1 million of the major
equipment directly from the suppliers, thereby allowing the
City to re-bid the project in December 2003, and award the
contract to BRB.
|