[ Overview ]
Project Description
New wastewater pump station which included site clearing, tree removal, 45 ft. deep excavation, heavy concrete cast in place structure of 2,103 CY in pump station and 138 CY for rest of the job, 4 submersible pumps 4,200 GPM each = 24.19 MGD capacity, two submerged mixers, two fine screens ,two screen compactors, one channel monster grinder, two odor control units, 37′ x 21′ metal building, 1,740 LF of pipe 36 inch DIP to 4 inch DIP, 411 LF of PVC pipe 24 ” to 2″, four manholes up to 27 ft. tall, seven slide gates 24×36 to 54×54 inch, instrumentation, electrical, 500 KW generator, painting, misc. metals, masonry building, flow meter, trolley hoist, fencing, sod, gravel surfacing, concrete paving and site grading.