[ Overview ]
Project Description
Replace all piping, valves, pumps (3 each pumps 2,400 gpm = 10.37 MGD & PS # 5 = 1,150 gpm = 4.97 MGD), metal stairs, grating, hatches, monorail lift system concrete shaping, install concrete decks and slabs inside two pump stations, concrete paving, fencing, electrical system replacement, new instrumentation, storm draining piping, bypass pump all sewage flows, concrete retaining wall