[ Overview ]

Project Description

The project consists of providing all labor, materials and subcontractors to construct a new mechanical wastewater treatment plant. It includes site grading, excavation, influent and effluent lift stations, yard pipe 915 LF of DIP 4″ – 12″, 4,020 LF of 8″ PVC effluent force main, 1,471 SY of concrete paving, fence, seeding, 886 CY of cast in place concrete for 10 structures, misc. metals, painting, office building which includes, drywall, ceilings, flooring, cabinets, bathroom, process equipment includes SBR equipment, fine scree, pumps, disinfection equipment, sludge containers, polymer system, SCADA, electrical, HVAC, Plumbing, prefabricated buildings, metal building and 15 precast structures/manholes.